Why Mediate a Land Use Dispute?

Marshall Berger | Pullman & Comley When disputes arise over land use issues, whether it is the approval or denial of a land use application, we have traditionally turned to our judicial system for their resolution. Indeed, in Connecticut, we have been fortunate to have a Judicial Branch that has appropriately resolved those disputes. Nevertheless,… Continue reading Why Mediate a Land Use Dispute?

A Challenge Regarding the Interpretation of a Project Condition of Approval may be Filed More than 90 Days Following the Project Approval

David Blackwell | Allen Matkins On June 25, 2020, the Fifth Appellate District decided Honchariw v. County of Stanislaus, holding that an applicant’s challenge to a local agency’s interpretation of a project condition of approval was not barred by the Subdivision Map Act’s statute of limitations because it was not a challenge to the validity of a condition of approval.… Continue reading A Challenge Regarding the Interpretation of a Project Condition of Approval may be Filed More than 90 Days Following the Project Approval

%d bloggers like this: