{"id":898174,"date":"2020-11-04T16:12:13","date_gmt":"2020-11-04T23:12:13","guid":{"rendered":"https:\/\/www.myconstructionexpert.com\/blog\/?p=898174"},"modified":"2020-11-04T16:12:18","modified_gmt":"2020-11-04T23:12:18","slug":"contractors-burden-construction-delays","status":"publish","type":"post","link":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/","title":{"rendered":"Contractor&#8217;s Burden When It Comes To Delay"},"content":{"rendered":"\n<p>David Adelstein | <a href=\"https:\/\/www.floridaconstructionlegalupdates.com\/contractors-burden-when-it-comes-to-delay\/\" target=\"_blank\" rel=\"noreferrer noopener nofollow\">Florida Construction Legal Updates<\/a><\/p>\n\n\n\n<p>When a contractor is challenging the assessment of\u00a0<a href=\"https:\/\/www.myconstructionexpert.com\/blog\/liquidated-damages-construction-delay\/\" target=\"_blank\" rel=\"noreferrer noopener\">liquidated damages<\/a>, or arguing that it is entitled to extended general conditions, the contractor bears a burden of proof to establish there were\u00a0<a href=\"https:\/\/www.myconstructionexpert.com\/blog\/looking-excuse-four-excusable-delays-construction-projects\/\" target=\"_blank\" rel=\"noreferrer noopener\">excusable delays<\/a>\u00a0that impacted the critical path and, in certain scenarios, the delays were not\u00a0<a href=\"https:\/\/www.myconstructionexpert.com\/blog\/looking-excuse-four-excusable-delays-construction-projects\/\" target=\"_blank\" rel=\"noreferrer noopener\">concurrent<\/a>\u00a0with contractor-caused delay:<\/p>\n\n\n\n<p><strong>When delays are&nbsp;<u>excusable<\/u>, a contractor is entitled to a time extension, such that the government may not assess liquidated damages for those delays.&nbsp; The government bears the initial burden of proving that the contractor failed to meet the&nbsp;<u>contract completion date<\/u>, and that the period of time for which the government assessed liquidated damages was correct. If the government makes such a showing, the&nbsp;<u>burden shifts to the contractor<\/u>&nbsp;to show that its failure to timely complete the work was excusable. To show an&nbsp;<u>excusable delay<\/u>, a contractor must show that the delay resulted from \u201cunforeseeable causes beyond the control and without the fault or negligence of the Contractor.\u201d&nbsp; \u201cIn addition, the unforeseeable cause must delay the overall contract completion;&nbsp;<em>i.e.<\/em>, it must affect the&nbsp;<u>critical<\/u><u>path<\/u>&nbsp;of performance.\u201d Further, the contractor must show that there was no&nbsp;<u>concurrent<\/u><u>delay<\/u>.<\/strong><\/p>\n\n\n\n<p><em>Ken Laster Co<\/em>., ASBCA No. 61292, 2020 WL 5270322 (ASBCA 2020) (internal citations omitted).<\/p>\n\n\n\n<p>Arguing delay without understanding your burden of proof obligations will be problematic, as the contractor in&nbsp;<em>Ken Laster<\/em>&nbsp;found out.&nbsp; In this dispute, a contractor was issued task orders to repair, prepare and plaint certain floating structures pursuant to task orders.&nbsp; The contractor was liable for liquidated damages if it did not timely complete the work. &nbsp;The contractor completed the work 289 days late and the government assessed liquidated damages.&nbsp; The contractor challenged the assessment of liquidated damages. However, the contractor did NOT show how anything it claimed the government did to delay completion impacted the&nbsp;<strong>critical path<\/strong>&nbsp;or that there was no&nbsp;<strong>concurrent delay<\/strong>.&nbsp; Without such showing, the contractor was unable to establish that liquidated damages were improper as it was unable to show there was excusable delay or that the delay to the critical path it caused was concurrent with an owner-caused delay to the critical path.<\/p>\n\n\n\n<p>Remember, if you are a contractor challenging the assessment of liquidated damages and\/or claiming you are entitled to delay damages (extended general conditions), you have a burden of proof. &nbsp;You will want to establish that there was excusable delay,&nbsp;<em>i.e.<\/em>, owner-caused delay, that impacted the critical path of the project resulting in the delay to the completion date, and the excusable delay was not concurrent with delay you caused to the completion date. &nbsp;This burden will routinely require expert opinion that will need to analyze schedules and contemporaneous project documentation to render these opinions (that there was excusable delay, the delay impacted the critical path, and in certain scenarios, the excusable delay was not concurrent). &nbsp;&nbsp;<strong>It is important to note, however, that if you are able to establish there was concurrent delay, you would still typically be entitled to a time extension, however, you would not be entitled to compensation for the delay (extended general conditions)<\/strong>. &nbsp;But, the burden is still on you to establish there was concurrent delay.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>David Adelstein | Florida Construction Legal Updates When a contractor is challenging the assessment of\u00a0liquidated damages, or arguing that it is entitled to extended general conditions, the contractor bears a burden of proof to establish there were\u00a0excusable delays\u00a0that impacted the critical path and, in certain scenarios, the delays were not\u00a0concurrent\u00a0with contractor-caused delay: When delays are&nbsp;excusable,&hellip; <a class=\"more-link\" href=\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\">Continue reading <span class=\"screen-reader-text\">Contractor&#8217;s Burden When It Comes To Delay<\/span><\/a><\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"jetpack_post_was_ever_published":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","enabled":false},"version":2}},"categories":[14],"tags":[9895,9252,11338,9112],"class_list":["post-898174","post","type-post","status-publish","format-standard","hentry","category-construction-2","tag-advise-consult","tag-concurrent-delay","tag-excusable-delay","tag-liquidated-damages","entry"],"jetpack_publicize_connections":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v25.0 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Contractor&#039;s Burden When It Comes To Delay - Advise &amp; Consult, Inc.<\/title>\n<meta name=\"description\" content=\"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Contractor&#039;s Burden When It Comes To Delay - Advise &amp; Consult, Inc.\" \/>\n<meta property=\"og:description\" content=\"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\" \/>\n<meta property=\"og:site_name\" content=\"Advise &amp; Consult, Inc.\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/\" \/>\n<meta property=\"article:published_time\" content=\"2020-11-04T23:12:13+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2020-11-04T23:12:18+00:00\" \/>\n<meta name=\"author\" content=\"admin\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@adviseconsult\" \/>\n<meta name=\"twitter:site\" content=\"@adviseconsult\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"admin\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\"},\"author\":{\"name\":\"admin\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7\"},\"headline\":\"Contractor&#8217;s Burden When It Comes To Delay\",\"datePublished\":\"2020-11-04T23:12:13+00:00\",\"dateModified\":\"2020-11-04T23:12:18+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\"},\"wordCount\":562,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\"},\"keywords\":[\"Advise &amp; Consult\",\"Concurrent Delay\",\"Excusable Delay\",\"Liquidated Damages\"],\"articleSection\":[\"Construction\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\",\"name\":\"Contractor's Burden When It Comes To Delay - Advise &amp; Consult, Inc.\",\"isPartOf\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#website\"},\"datePublished\":\"2020-11-04T23:12:13+00:00\",\"dateModified\":\"2020-11-04T23:12:18+00:00\",\"description\":\"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path\",\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/\"]}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#website\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/\",\"name\":\"Advise &amp; Consult, Inc.\",\"description\":\"Construction Expert Witnesses\",\"publisher\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/www.myconstructionexpert.com\/blog\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\",\"name\":\"Advise & Consult\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png\",\"contentUrl\":\"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png\",\"width\":162,\"height\":75,\"caption\":\"Advise & Consult\"},\"image\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/\",\"https:\/\/x.com\/adviseconsult\",\"https:\/\/www.linkedin.com\/company-beta\/204526\/\",\"https:\/\/www.youtube.com\/user\/MrConstructionExpert\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7\",\"name\":\"admin\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg\",\"caption\":\"admin\"},\"sameAs\":[\"http:\/\/www.expertwitnessinconstruction.com\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Contractor's Burden When It Comes To Delay - Advise &amp; Consult, Inc.","description":"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/","og_locale":"en_US","og_type":"article","og_title":"Contractor's Burden When It Comes To Delay - Advise &amp; Consult, Inc.","og_description":"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path","og_url":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/","og_site_name":"Advise &amp; Consult, Inc.","article_publisher":"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/","article_published_time":"2020-11-04T23:12:13+00:00","article_modified_time":"2020-11-04T23:12:18+00:00","author":"admin","twitter_card":"summary_large_image","twitter_creator":"@adviseconsult","twitter_site":"@adviseconsult","twitter_misc":{"Written by":"admin","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/#article","isPartOf":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/"},"author":{"name":"admin","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7"},"headline":"Contractor&#8217;s Burden When It Comes To Delay","datePublished":"2020-11-04T23:12:13+00:00","dateModified":"2020-11-04T23:12:18+00:00","mainEntityOfPage":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/"},"wordCount":562,"commentCount":0,"publisher":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization"},"keywords":["Advise &amp; Consult","Concurrent Delay","Excusable Delay","Liquidated Damages"],"articleSection":["Construction"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/","url":"https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/","name":"Contractor's Burden When It Comes To Delay - Advise &amp; Consult, Inc.","isPartOf":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#website"},"datePublished":"2020-11-04T23:12:13+00:00","dateModified":"2020-11-04T23:12:18+00:00","description":"the contractor bears a burden of proof to establish there were excusable delays that impacted the critical path","inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.myconstructionexpert.com\/blog\/contractors-burden-construction-delays\/"]}]},{"@type":"WebSite","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#website","url":"https:\/\/www.myconstructionexpert.com\/blog\/","name":"Advise &amp; Consult, Inc.","description":"Construction Expert Witnesses","publisher":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.myconstructionexpert.com\/blog\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization","name":"Advise & Consult","url":"https:\/\/www.myconstructionexpert.com\/blog\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/","url":"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png","contentUrl":"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png","width":162,"height":75,"caption":"Advise & Consult"},"image":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/","https:\/\/x.com\/adviseconsult","https:\/\/www.linkedin.com\/company-beta\/204526\/","https:\/\/www.youtube.com\/user\/MrConstructionExpert"]},{"@type":"Person","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7","name":"admin","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg","caption":"admin"},"sameAs":["http:\/\/www.expertwitnessinconstruction.com"]}]}},"jetpack_featured_media_url":"","jetpack_sharing_enabled":true,"jetpack_shortlink":"https:\/\/wp.me\/p2ztG6-3LEG","jetpack_likes_enabled":true,"_links":{"self":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898174","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/comments?post=898174"}],"version-history":[{"count":1,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898174\/revisions"}],"predecessor-version":[{"id":898175,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898174\/revisions\/898175"}],"wp:attachment":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/media?parent=898174"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/categories?post=898174"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/tags?post=898174"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}