{"id":898391,"date":"2021-01-13T14:24:58","date_gmt":"2021-01-13T21:24:58","guid":{"rendered":"https:\/\/www.myconstructionexpert.com\/blog\/?p=898391"},"modified":"2021-01-13T14:25:01","modified_gmt":"2021-01-13T21:25:01","slug":"time-limits-clause","status":"publish","type":"post","link":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/","title":{"rendered":"Time is of the Essence, Even When the Contract Doesn\u2019t Say So"},"content":{"rendered":"\n<p>Christopher G. Hill | <a href=\"https:\/\/constructionlawva.com\/time-is-of-the-essence-even-when-the-contract-doesnt-say-so\/?utm_source=feedburner&amp;utm_medium=email&amp;utm_campaign=Feed%3A+ConstructionLawMusings-RichmondVa+%28Construction+Law+Musings-+Richmond%2C+VA%29\" target=\"_blank\" rel=\"noreferrer noopener nofollow\">Construction Law Musings<\/a><\/p>\n\n\n\n<p>Welcome to 2021!\u00a0 As often happens here at\u00a0Construction Law Musings, the year starts with a few posts on notable construction law cases that dropped in the past year or so.\u00a0 Not only does this review hopefully help you keep up, but helps me keep up with the latest developments (one of the reasons\u00a0why I keep blogging).<\/p>\n\n\n\n<p>The first of these cases is\u00a0Appalachian Power Co. v. Wagman Heavy Civil, Inc.\u00a0out of the Western District of Virginia federal court. In this case, Wagman Heavy Civil, Inc. (\u201cWagman\u201d) and the Virginia Department of\u00a0 Transportation (\u201cVDOT\u201d) contracted for the design and construction of a highway interchange project (the \u201cProject\u201d). Wagman and the Appalachian Power Company (\u201cAPCO\u201d) entered into a written contract (the \u201cWritten Contract\u201d) for APCO to remove and relocate its utility structures (the \u201cWork\u201d) in order to facilitate construction for the Project.<\/p>\n\n\n\n<p>APCO filed suit against Wagman for payment pursuant to the contract. In response, Wagman filed a counterclaim alleging $1,039,074.20 in delay damages resulting from APCO\u2019s breach of its obligations under the&nbsp; Written Contract to use its best efforts to perform the Work within a reasonable period. Wagman alternatively asserted damages resulting from APCO\u2019s breach of an unwritten contract (the \u201cUnwritten Contract\u201d).<\/p>\n\n\n\n<p>Needless to say, APCO filed a Motion to Dismiss both counts of the counterclaim.&nbsp; As to the first count, APCO claimed that the delay damages claim was without merit because there was no schedule of performance or \u201ctime is of the essence\u201d clause in the Written Contract and because delay damages are \u201cspecial damages\u201d that are not ordinarily anticipated.&nbsp; As to the second count, APCO claimed that Wagman did not plead the terms of the Unwritten Contract with the required specificity.<\/p>\n\n\n\n<p>The Court denied the Motion to Dismiss Count I stating that neither ground stated was adequate for dismissal.&nbsp; As to the delay claims, the Court stated as follows:<\/p>\n\n\n\n<blockquote class=\"wp-block-quote is-layout-flow wp-block-quote-is-layout-flow\"><p>[t]he Court will refrain from determining whether they should be analyzed in light of the merger clause or as a subsequent modification to the Written Contract. The Written Contract itself is silent as to the schedule for performance, and it has long been established under Virginia law that \u201cwhen a contract is silent as to the time within which an act is to be performed, the law implies a reasonable time.\u201d&nbsp; And, as the Supreme Court of Virginia has indicated, \u201cwhat constitutes a reasonable time is generally an issue to be decided by a properly instructed jury, under all circumstances of the case.\u201d Id. (ruling that the trial court erred in sustaining demurrer). At least at this stage in the litigation, contrary to APCO\u2019s contention, Wagman need not provide additional allegations as to the schedule for performance in order to adequately plead its claim.<\/p><\/blockquote>\n\n\n\n<p>As to the oral contract claim, the Court simply stated that the specifics were a matter of proof and not pleading.<\/p>\n\n\n\n<p>In short, and despite the fact that\u00a0contracts are king here in the Commonwealth of Virginia, the courts occasionally read reasonableness into a contract where the contract is silent like in this case.\u00a0 Would Wagman and APCO have been better off to have a <a href=\"https:\/\/www.myconstructionexpert.com\/blog\/avoid-delay-get-ready-pay-risks-time-essence-clauses\/\" target=\"_blank\" rel=\"noreferrer noopener\">time is of the essence clause<\/a>?\u00a0 Of course.\u00a0 It is always better to set the terms of the deal in writing.\u00a0 This case simply adds an argument for your local\u00a0Virginia construction attorney\u00a0in the event there is a timing hole in the contract.<\/p>\n\n\n\n<p>As always I recommend that you read the case for yourself and that you let me know if you have any thoughts.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Christopher G. Hill | Construction Law Musings Welcome to 2021!\u00a0 As often happens here at\u00a0Construction Law Musings, the year starts with a few posts on notable construction law cases that dropped in the past year or so.\u00a0 Not only does this review hopefully help you keep up, but helps me keep up with the latest&hellip; <a class=\"more-link\" href=\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\">Continue reading <span class=\"screen-reader-text\">Time is of the Essence, Even When the Contract Doesn\u2019t Say So<\/span><\/a><\/p>\n","protected":false},"author":1,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"jetpack_post_was_ever_published":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","enabled":false},"version":2}},"categories":[9],"tags":[9895,224,8780,357],"class_list":["post-898391","post","type-post","status-publish","format-standard","hentry","category-construction-contracts","tag-advise-consult","tag-construction-contract","tag-time-limits-clause","tag-virginia","entry"],"jetpack_publicize_connections":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v25.0 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.<\/title>\n<meta name=\"description\" content=\"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.\" \/>\n<meta property=\"og:description\" content=\"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\" \/>\n<meta property=\"og:site_name\" content=\"Advise &amp; Consult, Inc.\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/\" \/>\n<meta property=\"article:published_time\" content=\"2021-01-13T21:24:58+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2021-01-13T21:25:01+00:00\" \/>\n<meta name=\"author\" content=\"admin\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@adviseconsult\" \/>\n<meta name=\"twitter:site\" content=\"@adviseconsult\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"admin\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\"},\"author\":{\"name\":\"admin\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7\"},\"headline\":\"Time is of the Essence, Even When the Contract Doesn\u2019t Say So\",\"datePublished\":\"2021-01-13T21:24:58+00:00\",\"dateModified\":\"2021-01-13T21:25:01+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\"},\"wordCount\":614,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\"},\"keywords\":[\"Advise &amp; Consult\",\"Construction Contract\",\"Time Limits Clause\",\"Virginia\"],\"articleSection\":[\"Construction Contracts\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\",\"name\":\"Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.\",\"isPartOf\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#website\"},\"datePublished\":\"2021-01-13T21:24:58+00:00\",\"dateModified\":\"2021-01-13T21:25:01+00:00\",\"description\":\"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent\",\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/\"]}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#website\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/\",\"name\":\"Advise &amp; Consult, Inc.\",\"description\":\"Construction Expert Witnesses\",\"publisher\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/www.myconstructionexpert.com\/blog\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#organization\",\"name\":\"Advise & Consult\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png\",\"contentUrl\":\"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png\",\"width\":162,\"height\":75,\"caption\":\"Advise & Consult\"},\"image\":{\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/\"},\"sameAs\":[\"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/\",\"https:\/\/x.com\/adviseconsult\",\"https:\/\/www.linkedin.com\/company-beta\/204526\/\",\"https:\/\/www.youtube.com\/user\/MrConstructionExpert\"]},{\"@type\":\"Person\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7\",\"name\":\"admin\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg\",\"caption\":\"admin\"},\"sameAs\":[\"http:\/\/www.expertwitnessinconstruction.com\"]}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.","description":"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/","og_locale":"en_US","og_type":"article","og_title":"Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.","og_description":"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent","og_url":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/","og_site_name":"Advise &amp; Consult, Inc.","article_publisher":"https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/","article_published_time":"2021-01-13T21:24:58+00:00","article_modified_time":"2021-01-13T21:25:01+00:00","author":"admin","twitter_card":"summary_large_image","twitter_creator":"@adviseconsult","twitter_site":"@adviseconsult","twitter_misc":{"Written by":"admin","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/#article","isPartOf":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/"},"author":{"name":"admin","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7"},"headline":"Time is of the Essence, Even When the Contract Doesn\u2019t Say So","datePublished":"2021-01-13T21:24:58+00:00","dateModified":"2021-01-13T21:25:01+00:00","mainEntityOfPage":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/"},"wordCount":614,"commentCount":0,"publisher":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization"},"keywords":["Advise &amp; Consult","Construction Contract","Time Limits Clause","Virginia"],"articleSection":["Construction Contracts"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/","url":"https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/","name":"Time is of the Essence, Even When the Contract Doesn\u2019t Say So - Advise &amp; Consult, Inc.","isPartOf":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#website"},"datePublished":"2021-01-13T21:24:58+00:00","dateModified":"2021-01-13T21:25:01+00:00","description":"despite contracts being king here in Virginia, the courts occasionally read reasonableness into a contract where the contract is silent","inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.myconstructionexpert.com\/blog\/time-limits-clause\/"]}]},{"@type":"WebSite","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#website","url":"https:\/\/www.myconstructionexpert.com\/blog\/","name":"Advise &amp; Consult, Inc.","description":"Construction Expert Witnesses","publisher":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.myconstructionexpert.com\/blog\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#organization","name":"Advise & Consult","url":"https:\/\/www.myconstructionexpert.com\/blog\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/","url":"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png","contentUrl":"https:\/\/www.myconstructionexpert.com\/blog\/wp-content\/uploads\/2015\/11\/AC-Red-Logo.png","width":162,"height":75,"caption":"Advise & Consult"},"image":{"@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/Advise-Consult-Inc-126949043996790\/","https:\/\/x.com\/adviseconsult","https:\/\/www.linkedin.com\/company-beta\/204526\/","https:\/\/www.youtube.com\/user\/MrConstructionExpert"]},{"@type":"Person","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/0a11abe008083d5fb19c2b0feefe7bd7","name":"admin","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.myconstructionexpert.com\/blog\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/b01e71b7acadd7657af782b7ad1a30cc?s=96&d=mm&r=pg","caption":"admin"},"sameAs":["http:\/\/www.expertwitnessinconstruction.com"]}]}},"jetpack_featured_media_url":"","jetpack_sharing_enabled":true,"jetpack_shortlink":"https:\/\/wp.me\/p2ztG6-3LIb","jetpack_likes_enabled":true,"_links":{"self":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898391","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/comments?post=898391"}],"version-history":[{"count":1,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898391\/revisions"}],"predecessor-version":[{"id":898392,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/posts\/898391\/revisions\/898392"}],"wp:attachment":[{"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/media?parent=898391"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/categories?post=898391"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.myconstructionexpert.com\/blog\/wp-json\/wp\/v2\/tags?post=898391"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}