Board Rules Contractor Entitled to Additional Costs After Government Unreasonably Refuses to Accept Equivalent Substitute

Sabah Petrov | Bradley In Appeal of Carothers Constr., Inc., the Armed Services Board of Contract Appeals (the “Board”) rejected the Government’s reliance on strict compliance with the material specifications for a 2 1/2″ thick roof deck product when the contractor proved the substitute 2″ thick roof deck was equivalent. While generally, the owner is entitled… Continue reading Board Rules Contractor Entitled to Additional Costs After Government Unreasonably Refuses to Accept Equivalent Substitute